Year 1 | Year 2 | Year 3 | Year 4
Year 1
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS1 | Consortium Agreement | 1 | M1 | 20/10/2013 | Achieved | Report |
MS2 | EuCARD-2 kick-off meeting | 1 | M1 | 18/09/2013 | Achieved | Report |
MS3 | EuCARD-2 project website launched | 1 | M1 | 20/04/2013 | Achieved | Report |
MS4 | EuCAN web pages available | 1 | M2 | 07/10/2013 | Achieved | Report |
MS41 | First workshop of Collective effects in Low Emittance Rings | 6 | M6 | 09/05/2014 | Achieved | Report |
MS73 | Commissioning of the SAPI for operation with metal photocathodes | 12 | M8 | 10/02/2014 | Achieved | Report |
MS42 | First workshop of Low Emittance Rings Technology | 6 | M9 | 29/07/2014 | Achieved | Report |
MS5 | Organization of the 1st Annual EuCARD-2 Collaboration Meeting | 1 | M12 | 17/07/2014 | Achieved | Report |
MS21 | Preliminary list of accelerator applications and candidate technologies | 4 | M12 | 22/01/2014 | Achieved | Report |
MS22 | Possible applications for neutron production targets | 4 | M12 | 16/05/2014 | Achieved | Report |
MS23 | First annual AccApplic workshop | 4 | M12 | 25/06/2014 | Achieved | Report |
MS29 | 1st XCOLL topical workshop | 5 | M12 | 20/01/2014 | Achieved | Report |
MS30 | 1st XRING topical workshop | 5 | M12 | 31/03/2014 | Achieved | Report |
MS31 | 1st XLINAC topical workshop | 5 | M12 | 28/04/2014 | Achieved | Report |
MS32 | 1st XPOL topical workshop | 5 | M12 | 04/04/2014 | Achieved | Report |
MS43 | Annual LOW-e-RING workshop, first year | 6 | M12 | 28/11/2013 | Achieved | Report |
MS58 | EuroNNAc2 2013 workshop | 7 | M12 | 04/11/2014 | Achieved | Report |
MS62 | Organized collaboration with DOE Program Bi-2212 | 10 | M12 | 21/07/2014 | Achieved | Report |
MS63 | Cable concept design report | 10 | M12 | 09/05/2014 | Achieved | Report |
MS69 | Irradiate first sample | 11 | M12 | 12/08/2014 | Achieved | Report |
MS74 | Design concept RF front end | 12 | M12 | 11/06/2014 | Achieved | Report |
MS89 | Demonstration and characterization of spatial and temporal synchronization of laser and electron beam | 13 | M12 | 17/04/2014 | Achieved | Report |
Year 2
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS24 | Summary of existing applications of low energy accelerators and the technology used | 4 | M14 | 14/07/2014 | Achieved | Report |
MS16 | Heat recovery workshop | 3 | M15 | 23/06/2014 | Achieved | Report |
MS6 | Summary of year 1 communication and publication activities | 1 | M18 | 10/11/2014 | Achieved | Report included in 1st Periodic Report |
MS13 | EuCARD-2 meets Industry event #1 | 2 | M18 | 20/05/2015 | Achieved | Report |
MS17 | Transport channels workshop | 3 | M18 | 05/12/2014 | Achieved | Report |
MS25 | Assessment of the state of the art of intermediate energy proton and ion accelerators | 4 | M18 | 26/09/2014 | Achieved | Report |
MS26 | Requirements for ADS | 4 | M18 | 29/10/2014 | Achieved | Report |
MS44 | First workshop of Low Emittance lattice design | 6 | M18 | 30/04/2015 | Achieved | Report |
MS64 | YBCO magnet design completion | 10 | M18 | 21/10/2014 | Achieved | Report |
MS75 | Investigation of quantum yield and energy spectrum of the electrons, emitted from the metal photocat | 12 | M18 | 17/10/2014 | Achieved | Report |
MS90 | Development and characterization of a new gas target system that includes a controllable, well-local | 13 | M18 | 07/10/2014 | Achieved | Report |
MS91 | Simulation of SPS beam self-modulation in plasma including seeding by laser and (optionally) by a sh | 13 | M18 | 07/10/2014 | Achieved | Report |
MS18 | Energy Storage workshop | 3 | M22 | 06/11/2015 | Achieved | Report |
MS7 | Organization of the 2nd Annual EuCARD-2 Collaboration Meeting | 1 | M24 | 30/04/2015 | Achieved | Report |
MS8 | EuCARD-2 mid-term Review | 1 | M24 | 21/05/2015 | Achieved | Report |
MS19 | Survey on candidates for VPP in accelerator labs | 3 | M24 | 16/12/2015 | Achieved | Report |
MS27 | Second annual AccApplic workshop | 4 | M24 | 30/04/2015 | Achieved | Report |
MS33 | 2nd XCOLL topical workshop | 5 | M24 | 28/04/2015 | Achieved | Report |
MS34 | 2nd XRING topical workshop | 5 | M24 | 07/01/2015 | Achieved | Report |
MS35 | 2nd XLINAC topical workshop | 5 | M24 | 08/07/2015 | Achieved | Report |
MS36 | 2nd XPOL topical workshop | 5 | M24 | 12/11/2015 | Achieved | Report |
MS45 | Annual LOW-e-RING workshop, second year | 6 | M24 | 28/10/2014 | Achieved | Report |
MS59 | EuroNNAc2 2014 workshop | 7 | M24 | 28/04/2015 | Achieved | Report |
MS70 | Present results on material damage from irradiation | 11 | M24 | 09/12/2016 | Achieved | Report |
MS71 | Show new material development status | 11 | M24 | 03/06/2015 | Achieved | Confidential |
MS76 | High power RF components fabricated and tested at low level | 12 | M24 | 30/04/2015 | Achieved | Report |
MS77 | Phase stabilisation experiment design | 12 | M24 | 30/04/2015 | Achieved | Report |
Year 3
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS65 | Test Station Kick-off | 10 | M26 | 08/07/2015 | Achieved | Report |
MS20 | Efficient RF Systems workshop | 3 | M27 | 17/12/2014 | Achieved | Report |
MS14 | EuCARD-2 meets Industry event #2 | 2 | M30 | 14/12/2015 | Achieved | Report |
MS46 | Second workshop of Collective effects in Low Emittance Rings | 6 | M30 | 20/05/2016 | Achieved | Report |
MS78 | Characterisation test facility implemented at HZB | 12 | M30 | 27/10/2015 | Achieved | Report |
MS79 | Crab cavity electromagnetic design | 12 | M30 | 29/02/2016 | Achieved | Report |
MS80 | Demonstrated operation of improved deposition system, Pb layers of 1 μm in thickness | 12 | M30 | 27/10/2015 | Achieved | Report |
MS92 | NRF operation established with closed beam based FB loop | 13 | M30 | Covered by Del13.5 | Achieved | Report |
MS93 | Diagnostic system installed and performance determined | 13 | M30 | 27/10/2015 | Achieved | Report |
MS66 | First Cable length for magnet winding | 10 | M32 | 22/12/2015 | Achieved | Report |
MS47 | Second workshop of Low Emittance Rings Technology | 6 | M33 | 22/06/2017 |
Achieved |
Report |
MS9 | Summary of year 2 communication and publication activities | 1 | M36 | 30/06/2015 | Achieved | Report included in 1st Periodic Report |
MS10 | Organization of the 3rd Annual EuCARD-2 Collaboration Meeting | 1 | M36 | 30/06/2016 | Achieved | Report |
MS28 | Third annual AccApplic workshop | 4 | M36 | 26/05/2016 | Achieved | Report |
MS37 | 3rd XCOLL topical workshop | 5 | M36 | 11/03/2016 | Achieved | Report |
MS38 | 3rd XRING topical workshop | 5 | M36 | 22/01/2016 | Achieved | Report |
MS39 | 3rd XLINAC topical workshop | 5 | M36 | 22/01/2016 | Achieved | Report |
MS40 | 3rd XPOL topical workshop | 5 | M36 | 20/06/2016 | Achieved | Report |
MS48 | Annual LOW-e-RING workshop, third year | 6 | M36 | 22/04/2016 | Achieved | Report |
MS49 | Second workshop of Low Emittance lattice design | 6 | M36 | 22/06/2017 | Achieved | Report |
MS60 | EuroNNAc2 2015 workshop | 7 | M36 | 21/04/2016 | Achieved | Report |
MS67 | Report on HE-LHC Main Dipole design | 10 | M36 | 30/06/2016 | Achieved | Report |
MS68 | Technical and economical comparison YBCO/Bi2212 magnets | 10 | M36 | 21/04/2016 | Achieved | Report |
MS81 | RF design CLIC_DDS_B FP and HOM couplers | 12 | M36 | 02/06/2017 | Achieved | Report |
MS82 | Completed coupled cavity simulations of 8-cavity module | 12 | M36 | 17/06/2016 | Achieved | Combined with D12.7 |
MS83 | Manufacturing and commissioning of the photocathode transport system | 12 | M36 | 21/04/2016 | Achieved | Report |
MS94 | Simulation of modular plasma configuration with beam guiding between plasma modules | 13 | M36 | 21/04/2016 | Achieved | Report |
Year 4
Mil. no. | Milestone name | WP no. | Planned delivery date | Actual delivery date | Status | Comments |
MS84 | Deposition test facility designed at CEA | 12 | M40 | Covered by Del12.10 | Achieved | Report |
MS15 | EuCARD-2 meets Industry event #3 | 2 | M42 | 21/12/2016 | Achieved | Report |
MS85 | Investigation of the brightness of different metal photocathodes in a S-band NCRF gun | 12 | M42 | 14/06/2017 | Achieved | Report |
MS72 | Present results on material damage from simulation and compare to experiments | 11 | M45 | Combined with Del11.4 | Achieved | Report |
MS86 | RF design of fully interleaved structure | 12 | M45 | 04/04/2017 | Achieved | Report |
MS11 | Summary of year 4 communication and publication activities | 1 | M48 | 30/06/2017 | Achieved | Report included in the 3rd Periodic Report. |
MS12 | Organization of the final Annual EuCARD-2 Collaboration Meeting | 1 | M48 | 29/05/2017 | Achieved | Report |
MS61 | EuroNNAc2 2016 workshop | 7 | M48 | 15/06/2017 | Achieved | Report |
MS87 | Fundamental physics report | 12 | M48 | 02/06/2017 | Achieved | Report |
MS88 | Report summarising the results obtained in characterising the various new thin film technologies | 12 | M48 | 02/06/2017 | Achieved | Report |